Application (repackaged) 7 September 2022
Additional assessments submitted December 2021 and April 2022
GWRC technical review of original application
Further information request 18 May 2022
Further information request 15 August 2022
Further information response 17 June 2022
Further information response 9 September 2022
Further information provided November 2022 - August 2023
GWRC technical review of repackaged application & further info - October 2022 to September 2023
Further information 2 April 2024
GWRC technical review of s92 response 2 April 2024
Further Information provided 29 May 2024
Further information provided 6 September 2024